List Power Plants Project Development 10.000 MW Second Phase Acceleration Program.

Power Plant by PLN :
1. PLTP Tangkuban Perahu I, Jawa Barat 2x55 MW.
2. PLTP Kamojang 5 & 6, Jawa Barat 1x40 MW & 1x60 MW.
3. PLTP Ijen, Jawa Timur, 2x55 MW.
4. PLTP Lyang Argopuro, Jawa Timur, 1x55 MW
5. PLTP Wilis/Ngebel, Jawa Timur, 3x55 MW.
6. PLTP Sungai Penuh, Jambi, 2x55 MW.
7. PLTU Hululais, Bengkulu, 2x55 MW.
8. PLTP Kotamobagu 1 & 2, Sulawesi Utara, 2x20 MW.
9. PLTP Kotamobagu 3 & 4, Sulawesi Utara, 2x20 MW.
10. PLTP Sembalun, Nusa Tenggara Barat, 2x10 MW.
11. PLTP Tulehu, Maluku, 2x10 MW.
12. PLTA Upper Cisokan, Jawa Barat, 4x250 MW.
13. PLTU Asahan 3, Sumatera Utara, 2x87 MW.
14. PLTU Indramayu, Jawa Barat, 1x1.000 MW
15. PLTU Pangkalan Susu 3 dan 4, Sumatera Utara, 2x200 MW.
16. PLTU Sampit, Kalimantan Tengah, 2x25 MW.
17. PLTU Kotabaru, Kalimantan Selatan, 2x7 MW.
18. PLTU Parit Baru, Kalimantan Barat, 2x50 MW
19. PLTU Talakar, Sulawesi Selatan, 2x100 MW.
20. PLTU Kaltim (Peaking) 2x50 MW
21. PLTGU Muara Tawar ad on 2,3 & 4, Jawa Barat 1x150 MW & 3x350 MW.

Power Plant by Private :
1. PLTP Rawa Dano, Banten, 1x110 MW.
2. PLTP Cibuni, Jawa Barat, 1x10 MW.
3. PLTP Cisolok-Cisukarame, Jawa Barat, 1x50 MW.
4. PLTP Drajat, Jawa Barat, 2x55 MW.
5. PLTP Karaha Bodas, Jawa Barat, 1x30 MW dan 2x55 MW.
6. PLTP Patuha, Jawa Barat, 3x60 MW.
7. PLTP Salak, Jawa Barat, 1x40 MW
8. PLTP Tampomas, Jawa Barat, 1x45 MW
9. PLTP Tangkuban Perahu II, Jawa Barat, 2x30 MW
10. PLTP Wayang Windu, Jawa Barat, 2x120 MW.
11. PLTP Baturaden, Jawa Tengah, 2x110 MW.
12. PLTP Dieng, Jawa Tengah, 1x55 MW & 1x60 MW.
13. PLTP Guci, Jawa Tengah, 1x55 MW
14. PLTP Ungaran, Jawa Tengah, 1x55 MW
15. PLTP Seulawah Agam, Nanggroe Aceh Darussalam, 1x55 MW
16. PLTP Jaboi, Nanggroe Aceh Darusalam, 1x7 MW
17. PLTP Sarulla 1, Sumatera Utara, 3x110 MW
18. PLTP Sarulla 2, Sumatera Utara, 2x55 MW
19. PLTP Sorik Merapi, Sumatera Utara, 1x55 MW
20. PLTP Muaralaboh, Sumatera Barat, 2x110 MW
21. PLTP Lumut Balai, Sumatera Selatan, 4x55 MW
22. PLTP Rantau Dadap, Sumatera Selatan, 2x110 MW.
23. PLTP Rajabasa, Lampung, 2x110 MW
24. PLTP Ulubelu 3 dan 4, Lampung, 2x55 MW.
25. PLTP Lahendong 5 dan 6, Sulawesi Utara, 2x20 MW.
26. PLTP Bora, Sulawesi Tengah, 1x5 MW
27. PLTP Merana/Masaingi, Sulawesi Tengah, 2x10 MW
28. PLTP Mangolo, Sulawesi Tenggara, 2x5 MW
29. PLTP Huu, Nusa Tenggara Barat, 2x10 MW
30. PLTP Atadei, Nusa Tenggara Timur, 2x2,5 MW.
31. PLTP Sukoria, Nusa Tenggara Timur, 2x2,5 MW.
32. PLTP Jailolo, Maluku Utara, 2x5 MW
33. PLTP Songa Wayaua, Maluku Utara, 1x5 MW
34. PLTA Simpang Aur, Bengkulu, 2x6MW & 2x9 MW
35. PLTU Bali Timur,Bali, 2x100 MW
36. PLTA Madura, 1x400 MW
37. PLTU Sabang, Nanggroe Aceh Darussalam, 2x4 MW
38. PLTU Nias, Sumatera Utara, 2x7 MW
39. PLTU Tanjung Pinang, Kepulauan Riau, 2x15 MW
40. PLTU Tanjung Balai Karimun, Kepulauan Riau, 2x10 MW
41. PLTU Tanjung Batu, Kepulauan Riau, 2x4 MW
42. PLTU Bangka, Bangka Belitung, 2x30 MW
43. PLTU Ketapang, Kalimantan Barat, 2x10 MW
44. PLTU Petung, Kalimantan Timur, 2x7 mW
45. PLTU Melak, Kalimantan Timur, 2x7 MW
46. PLTU Nunukan, Kalimantan Timur, 2x7 MW
47. PLTU Kaltim, 2x100 MW
48. PLTU Putussibau, Kalimantan Barat, 2x4 MW
49. PLTU Kalsel, Kalimantan Selatan, 2x100 MW
50. PLTU Tahuna, Sulawesi Utara, 2x4 MW
51. PLTU Moutong, Sulawesi Tengah, 2x4 MW
52. PLTU Luwuk, Sulawesi Tengah, 2x10 MW.
53. PLTU Mamuju, Sulawesi Barat, 2x7 MW
54. PLTU Selayar, Sulawesi Selatan, 2x4 MW
55. PLTU Bau-bau, Sulawesi Tenggara, 2x10 MW.
56. PLTU Kendari, Sulawesi Tenggara, 2x25 MW
57. PLTU Kolaka, Sulawesi Tenggara, 2x10 MW.
58. PLTU Sumbawa, Nusa Tenggara Barat, 2x10 MW
59. PLTU Larantuka, Nusa Tenggara Timur, 2x4 MW
60. PLTU Waingapu, Nusa Tenggara Timur, 2x4MW
61. PLTU Tobelo, Maluku Utara, 2x4 MW
62. PLTU Tidore, Maluku Utara, 2x7 MW
63. PLTU Tual, Maluku, 2x4 MW
64. PLTU Masohi, Maluku, 2x4 MW
65. PLTU Biak, Papua, 2x7 MW
66. PLTU Jayapura, Papua, 2x15 MW
67. PLTU Nabire, Papua, 2x7 MW
68. PLTU Merauke, Papua, 2x7 MW
69. PLTU Sorong, Papua Barat, 2x15 MW.
70. PLTU Andai, Papua Barat, 2x7 MW
71. PLTGU Bangkanai, Kalimantan Tengah, 1x120 MW
72. PLTGU Senoro, Sulawesi Tengah, 2x120 MW.

1 comment:

KHAIRIL ANWAR said...

Masa sih PLTA Madura berkapasitas 1x400 MW?? Memangnya bisa ya Pak PLTA membangkitkan daya sebesar itu???Kalo PLTU, PLTN atau PLTGU saya percaya.
Kalo memang benar lokasinya dimana pak?Yang saya tau di Madura tidak ada sungai besar. Apalagi kalo kemarau susah air disana.
Mohon penjelasannya yah Pak.